Tuesday, October 3, 2017

Interior Door Installation, Fireplace in Progress, Finish Carpentry Sketches, and Cabinetry Installation

Interior doors installed, waiting to be trimmed:



Living room fireplace has been tiled:

Wall sketches of custom built ins:

Living Room Fireplace, Design to Be Changed Slightly

Mud Room 

Master Bedroom Beverage Center

Cutout for Greg's Video Game Systems
Cabinets:
Kids Bathroom (Poor Lighting Due to Night Time and No Light Bulbs)

Master Bath

Laundry
Kitchen cabinets in process:






Someone is a little excited about her adjustable spice rick cabinets:


Kitchen cabinets almost complete:


Bonus pic-Wall paneling in Home Depot rental truck:



We are supposed to be moving in around Thanksgiving, (a month later than originally scheduled) but it still seems like there is so much more to be done - list off the top of my head:

Complete tiling in master bath
Tile fireplace in master bedroom
Trim all interior doors and windows
Aforementioned built ins
Finish staircase
Granite installation
Back splash installation
Sink installation
Landscaping (tentatively starting 10/9)
Painting
Staining
Appliance installation
Lighting installation (includes power outlets)
Plumbing installation
Miscellaneous hardware (door knobs, towel bars, etc) installation
Mirrors installation
Shower glass installation
Carpet installation
Closet organization installation

And then maybe we can finally move in, almost two years after this whole process began!